Oak Grove Renewable Energy Ltd is set in a rural location 10 miles north of Norwich in Norfolk.
The site was commissioned in 2015 and supplies electricity to the grid at a connection point approximately 400m from the site. Two engines generate the bulk o[f the electrical output, with an Organic Rankine Cycle using surplus heat to generate a further 125kW. The overall output is sufficient to provide all of the power required by 2500 homes.
The site sources feedstock from local farms as part of their rotational and sequential cropping programme assisting sustainable farming practicies leading to diversity, soil health and food productivity. Much of the digestate produced by the AD plant is returned to the farm land, which, as light soil provides significant and much needed organic matter.
Contact:
AD Plant:
Site Manager: Graham Moorhouse
Telephone: 07880 383336
Feedstock Manager: Karl Boldero
Telephone: 07787 100907
Hours of Operation:
AD Plant:
Appointments by arrangement